Beijing Daxing International Airport, with a total investment of about 80 billion yuan, covers an area of 23,210 acres and a total construction area of 1.4 million m². It will build 7 runways, 150 passenger planes, 24 cargo planes, 14 aircraft sites A 700,000-square-meter terminal building will be built for the maintenance of the apron. The main building and the finger gallery will meet the demand for 72 million and 45 million passengers, respectively. It is China's super-large international aviation comprehensive transportation hub.
◆ The PDU should have an alarm monitoring function, which can understand the running status, power consumption, and environmental status of each equipment in the equipment room in real time;
◆ When the server's power module is short-circuited or the device is overloaded, it should not cause trips to the same or higher-level circuit breakers, which will cause the entire cabinet equipment to lose power and risk A / B power switching;
◆ The PDU should be able to record the overall power consumption of the computer room and the power consumption of a server in the past;
◆ The PDU should be able to collect the energy consumption of a single device to provide data analysis for the PUE of the computer room;
◆ MPDU-B series
◆ Real-time monitoring and recording of power consumption of each server's current, voltage, power and energy through the MPDU-B series, which facilitates operation and maintenance personnel to remotely understand the operating status of equipment in the equipment room in real time, and provides accurate data references for PUE calculations in the data center;
◆ Through the external temperature sensor interface, customers can monitor the temperature change inside the cabinet in real time;
◆ The MPDU-B series has NET, SER, IN, OUT and other interfaces to meet customer power collection, transmission, monitoring and alarm functions.