Background

The The new National Museum in Norway costs US$ 6.6 billion and has a total area of 7 football fields. The new museum will serve the modern audience and the facilities and scenes will be presented in modern technology.  It also includes a enterprise private cloud data center with maximum 4MW power capacity.

 

挪威标志.jpg

 

Challenges and goals

◆  Remote monitoring of rack equipments power consumption and all PDU electrical parameter;

◆  Remote control the PDU outlets, switching off offline servers in time to reduce power consumption;

◆  Each PDU should have 3 phase input and11kW or 22kW power capacity;

  

Solutions

◆  CLEVER managed PDU – RPDU , outlet switched;

 

Benefits

◆  RPDU enables the administrators to monitor server and power equipment operations off-site without having to visit the site;

◆  RPDU enables the administrators to remotely switch on/off the IT equipments in the museum in real time as needed , thus saving the power consumption and labor costs;